January 12, 2015

Heavy winds at Puuska

Peikko delivered to a project of Rajakiiri/Puuska 2 in Tornio, Finland a total of 5 foundations. Another successful wind foundation project, with all components delivered according to the promise.

There were three foundation types; A11 (500kPa), A10,12,13 (250kpa) and A9 (300kPa). The delivery content was Mould, Modix center anchor, Anchor cage, Modix bars, PSB, spacer + common reinforcement + assembly work and concreting on site.
 
1. Ground levelling works done - first foundation ready for reinforcment works.  
 
 
2. Reinforcment ready for concreting
 
3
. Foundation concreted and covered. The covering was used for 3 weeks due to weather, but also to secure good hardering of the concrete.
 

4. Foundation ready for tower assembly.

 

 



 

 

 


 